MaginoProject Capital Estimate at Completion
Process Facilities (CAD M) Largely shielded from cost inflation in process facilities area due to EPC contract with Ausenco. Schedule Recovery • Delay in preparing foundation area has led to schedule compression, but overall schedule intact for first gold end of Q1 2023. Scope • Increased earthwork quantities.